Construction Updates

  • Construction began October 23, 2020
  • As new trades begin work on site, multiple trucks will be delivering materials to the site each day (Construction traffic will enter and leave the site from the entrances off of 12th street)
  • Shoring of the elevated deck will continue
  • Rebar install began on the elevated deck
  • First layer of exterior backfill will continue
  • First lift of the waterproofing on the outside face of foundation walls will continue
  • Digging of the west rampart will continue

Progress Videos

Time Lapse Video

Progress Photos

PAMPC Construction Update 3.5.21
Waterproofing being installed along north face of mechanical room wall
PAMPC Construction Update 3.5.21
View of the basement from Northeast corner
PC: Bob Elmore Photography
PAMPC Construction Update 3.19.21
Mechanical room waterproofed and backfilled with conduit install started
PC: Bob Elmore Photography
PAMPC Construction Update 3.19.21
Aerial view of basement
PC: Bob Elmore Photography
PAMPC Construction Update 3.5.21
View of the basement walls/columns from base of the ramp at the west side
PC: Bob Elmore Photography
PAMPC Construction Update 3.5.21
Site utilities work along northeast corner of the project area
PAMPC Construction Update 1.29.21
View of whole site with forms on north section of walls
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
Mechanical room after plumbing was installed and area was stoned
PC: Bob Elmore Photography
PAMPC Construction Update 1.22.21
View of mechanical room/south basement walls being poured at the southwest corner
PAMPC Construction Update 1.22.21
Interior column pads dug out in preparation for mud slab pours
PAMPC Construction Update 1.22.21
View of interior column pad footings covered in blankets and southeast wall stripped
PAMPC Construction Update 1.22.21
Southeast wall stripped and southwest wall covered in blankets
PAMPC Construction Update 1.29.21
View of the interior columns being poured at CL 7 & 8
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
Interior columns being poured
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
View of work on walls and interior columns
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
View of work on walls and interior columns
PC: Bob Elmore Photography