Construction Updates

  • Construction began October 23, 2020
  • As new trades begin work on site, multiple trucks will be delivering materials to the site each day (Construction traffic will enter and leave the site from the entrances off of 12th street)
  • Foundation walls have been waterproofed
  • Began installation of top layer of overhead plumbing in the mechanical room
  • Completed installation of underground gas pipe and chiller lines extending to the utility coral
  • Poured and stripped the interior concrete duct bank
  • Formed the loading dock footings and installed rebar
  • Topsoil will continue to be installed at wet ponds

Progress Videos

Time Lapse Video

Progress Photos

View of basement with foundation walls and temporary lighting
Loading dock footings and rebar install
Prep for steel lay down areas
Process of insulating and waterproofing the main basement
Shoring of the elevated deck
Elevated deck concrete pours
PAMPC Construction Update 3.5.21
Waterproofing being installed along north face of mechanical room wall
PAMPC Construction Update 3.5.21
View of the basement from Northeast corner
PC: Bob Elmore Photography
PAMPC Construction Update 3.19.21
Mechanical room waterproofed and backfilled with conduit install started
PC: Bob Elmore Photography
PAMPC Construction Update 3.19.21
Aerial view of basement
PC: Bob Elmore Photography
PAMPC Construction Update 3.5.21
View of the basement walls/columns from base of the ramp at the west side
PC: Bob Elmore Photography
PAMPC Construction Update 3.5.21
Site utilities work along northeast corner of the project area
PAMPC Construction Update 1.29.21
View of whole site with forms on north section of walls
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
Mechanical room after plumbing was installed and area was stoned
PC: Bob Elmore Photography
PAMPC Construction Update 1.22.21
View of mechanical room/south basement walls being poured at the southwest corner
PAMPC Construction Update 1.22.21
Interior column pads dug out in preparation for mud slab pours
PAMPC Construction Update 1.22.21
View of interior column pad footings covered in blankets and southeast wall stripped
PAMPC Construction Update 1.22.21
Southeast wall stripped and southwest wall covered in blankets
PAMPC Construction Update 1.29.21
View of the interior columns being poured at CL 7 & 8
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
Interior columns being poured
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
View of work on walls and interior columns
PC: Bob Elmore Photography
PAMPC Construction Update 1.29.21
View of work on walls and interior columns
PC: Bob Elmore Photography